Updated 3-26-20
There are no major disruptions in our supply chain, but here is a status update
with a breakdown of lead times and also recommendations for inventory.
RECOMMENDED SPARE PARTS IN-STOCK*
Disharge Seals
Door Gaskets
Seal Housing
Air Seal Kits
Cover Gaskets
Discharge Bearings
Safety Switches
*Most common spare parts are in-stock, but uncommon parts have a lead time of 2 – 3
weeks.
LONG LEAD TIME PARTS
Agitators | 8 – 10 weeks | |
Part | Factory Paint / Unpainted |
Washdown Paint |
Cylinders | 4-5 weeks | 7-9 weeks |
Motors | 1-3 weeks | 5-8 weeks |
Gear Motors | 2-3 weeks | 5-8 weeks |
Gearboxes | 2-3 weeks | 5-8 weeks |
We are working with required distancing and sanitation to help our customers
maintain their production schedule. Our parts and service specialists are on stand-by to
support you.
Contact parts@apachestainless.com or call 920-356-7347.